At 60 metres up from the ground the crane lowers the huge 12 ton gearbox and disk brake assembly in to position within the nacelle at Turbine No 11.
The engineers standing in the nacelle are in contact by radio with the crane operator down below LinkExternal link

Following a public inquiry held in 2004, planning consent was granted by the Secretary of State on the 25th May 2005 for the building of Scout Moor Wind Farm.
Construction of the wind turbines began back in November 2007 at Turbine No 16.
By June 2008 engineers had constructed 26 wind turbine towers and installed 78 turbine blades 450 metres above sea level on Scout Moor amid adverse weather conditions of thick fog, gale force winds, torrential rain, snow and ice during the winter months of 2008.

On the 25th of September 2008 dignitaries from across the North West were invited to the official opening of the Scout Moor wind farm.
Children from Edenfield Primary School, who have enjoyed lessons based around the wind farm, were on hand to cut the ribbon at Turbine No 22.LinkExternal link
Head Teacher at Edenfield Primary School, Janet Reidy, said: "It was superb for the children to be involved after all the work they had done about the wind farm in their lessons.
I think they will all remember this in future years and now they know what it's like to be film stars with all the camera crews there!"

Richard Dibley, wind power development manager at Peel, said at the opening: "We have welcomed people here today to thank them for their patience and understanding during the construction period and for them to see the wind farm in action at close quarters. I think we have chosen the perfect site here as it is more than 50% windier up here than it is in the surrounding area. These turbines will be generating power for years to come using a natural resource that will never run out."

SD8218 : Almost there
SD8218 : Gearbox , Rotor Shaft and Disk Brake Assembly for Turbine No 11
SD8218 : Gearbox , Rotor Shaft and Disk Brake Assembly for Turbine No 11
SD8417 : Working on the hub 60 metres up.
SD8418 : The very first completed wind turbine on Scout Moor
SD7919 : Last Turbine Tower Delivery to Scout Moor

Turbine details: Tower Height: 60m
Blade Length: 40m Total Max Height: 100m
Manufacturer: Nordex
Model: N80 LinkExternal link

Key Facts LinkExternal link

Scout Moor Wind Farm Construction Picture Gallery
LinkExternal link
Creative Commons Licence [Some Rights Reserved]   © Copyright Paul Anderson and licensed for reuse under this Creative Commons Licence.
year taken
2008
1:50,000 Modern Day Landranger(TM) Map © Crown Copyright
+
1:50,000 Modern Day Landranger(TM) Map © Crown Copyright
TIP: Click the map for Large scale mapping
Change to interactive Map >
Grid Square
SD8218, 147 images   (more nearby)
Photographer
  (find more nearby)
Image classification?
Supplemental image
Date Taken
Thursday, 1 May, 2008   (more nearby)
Submitted
Monday, 3 November, 2008
Category
Wind turbines   (more nearby)
Subject Location
OSGB36: geotagged! SD 8245 1812 [10m precision]
WGS84: 53:39.5563N 2:16.0224W
Photographer Location
OSGB36: geotagged! SD 8245 1812
View Direction
NORTH (about 0 degrees)
Looking for a postcode? Try this pageExternal link
Clickable map
+

This page has been viewed about 429 times.
View this location: KML (Google Earth) · Google MapsExternal link · OS Map Checksheet · Geograph Map · geotagged! More Links for this image
NW N NE
W Go E
SW S SE
[Mark
You are not logged in login | register
please donate