SD8218 : Scout Moor Wind Farm Turbine Tower No 14
near to Cheesden, Rochdale, Great Britain

Scout Moor Wind Farm Turbine Tower No 14
The wind turbine in the foreground is Turbine Tower No 14 which was completed on the 29th of April 2008.
SD8417 : View from the top of Turbine Tower No 10 looking North West
SD8418 : The very first completed wind turbine on Scout Moor
SD8417 : Turbine Tower No 10 under construction
SD8417 : Working on the hub 60 metres up.
SD8317 : Aerial View of Scout Moor Wind Farm
SD7919 : Turbine tower section passing Edenfield Primary School
Turbine details: Tower Height: 60m
Blade Length: 40m Total Max Height: 100m
Manufacturer: Nordex
Model: N80 Link
Map showing stage of construction at beginning of May 2008 Link
Key Facts Link
Scout Moor Wind Farm Construction Picture Gallery
Link
Following a public inquiry held in 2004, planning consent was granted by the Secretary of State on the 25th May 2005 for the building of Scout Moor Wind Farm.
Construction of the wind turbines began back in November 2007 at Turbine No 16.
By June 2008 engineers had constructed 26 wind turbine towers and installed 78 turbine blades 450 metres above sea level on Scout Moor amid adverse weather conditions of thick fog,gale force winds,torrential rain,snow and ice during the winter months of 2008.
On the 25th of September 2008 dignitaries from across the North West were invited to the official opening of the Scout Moor wind farm.
Children from Edenfield Primary School, who have enjoyed lessons based around the wind farm, were on hand to cut the ribbon at Turbine No 22.Link
Head Teacher at Edenfield Primary School, Janet Reidy, said: "It was superb for the children to be involved after all the work they had done about the wind farm in their lessons.
I think they will all remember this in future years and now they know what it's like to be film stars with all the camera crews there!"
Richard Dibley, wind power development manager at Peel, said at the opening: "We have welcomed people here today to thank them for their patience and understanding during the construction period and for them to see the wind farm in action at close quarters. I think we have chosen the perfect site here as it is more than 50% windier up here than it is in the surrounding area. These turbines will be generating power for years to come using a natural resource that will never run out."
SD8417 : View from the top of Turbine Tower No 10 looking North West
SD8418 : The very first completed wind turbine on Scout Moor
SD8417 : Turbine Tower No 10 under construction
SD8417 : Working on the hub 60 metres up.
SD8317 : Aerial View of Scout Moor Wind Farm
SD7919 : Turbine tower section passing Edenfield Primary School
Turbine details: Tower Height: 60m
Blade Length: 40m Total Max Height: 100m
Manufacturer: Nordex
Model: N80 Link
Map showing stage of construction at beginning of May 2008 Link
Key Facts Link
Scout Moor Wind Farm Construction Picture Gallery
Link
Following a public inquiry held in 2004, planning consent was granted by the Secretary of State on the 25th May 2005 for the building of Scout Moor Wind Farm.
Construction of the wind turbines began back in November 2007 at Turbine No 16.
By June 2008 engineers had constructed 26 wind turbine towers and installed 78 turbine blades 450 metres above sea level on Scout Moor amid adverse weather conditions of thick fog,gale force winds,torrential rain,snow and ice during the winter months of 2008.
On the 25th of September 2008 dignitaries from across the North West were invited to the official opening of the Scout Moor wind farm.
Children from Edenfield Primary School, who have enjoyed lessons based around the wind farm, were on hand to cut the ribbon at Turbine No 22.Link
Head Teacher at Edenfield Primary School, Janet Reidy, said: "It was superb for the children to be involved after all the work they had done about the wind farm in their lessons.
I think they will all remember this in future years and now they know what it's like to be film stars with all the camera crews there!"
Richard Dibley, wind power development manager at Peel, said at the opening: "We have welcomed people here today to thank them for their patience and understanding during the construction period and for them to see the wind farm in action at close quarters. I think we have chosen the perfect site here as it is more than 50% windier up here than it is in the surrounding area. These turbines will be generating power for years to come using a natural resource that will never run out."
year taken
2008
TIP: Click the map to open OS Get-a-Map
Change to interactive Map >
Change to interactive Map >
- Grid Square
- SD8218, 139 images (more nearby)
- Photographer
- Paul Anderson (find more nearby)
- Image classification
- Geograph
- Date Taken
- Thursday, 1 May, 2008 (more nearby)
- Submitted
- Thursday, 15 January, 2009
- Category
- Wind farm (more nearby)
- Subject Location
-
OSGB36:
SD 827 181 [100m precision]
WGS84: 53:39.5460N 2:15.7954W - Photographer Location
-
OSGB36:
SD 826 180 - View Direction
- East-northeast (about 67 degrees)
Looking for a postcode? Try this page
This page has been viewed about 63 times. Read more
View this location:
KML (Google Earth),
Google Maps
,
OS Get-a-map™
,
OS Map Checksheet,
Geograph Map,
More Links for this image
![Creative Commons Licence [Some Rights Reserved]](http://creativecommons.org/images/public/somerights20.gif)