West Loch Awe Timber Haul Route :: Shared Description
The West Loch Awe Timber Haul Route (WLATHR) is a 35km (22 miles) timber haul route that is being jointly developed by The Forestry Commission and GreenPower (Carraig Gheal) Ltd. The road will be used for turbine component delivery to the 46MW Carraig Gheal wind farm site and provide a strategic route in perpetuity for timber haulage through the Inverliever, Inverinan and Nant forests. Much of the route comprises existing forestry roads in place as part of the strategic timber transport route network, although upgrading is required for wind turbine component loads.
The majority of funding is coming from GreenPower (Carraig Gheal) Ltd with additional co-finance from Forestry Commission Scotland and Argyll and Bute Council. Forestry Commission Scotland have awarded £1,000,000 towards the overall £5,300,000 cost from the Strategic Timber Transport Fund.
The southern limit of the WLATHR is on the A816 at Salachary and the northern limit on the B845 at Kilchrenan. When complete, the road will take about 4,200 timber lorry movements each year off the single-track roads that serve the villages of Ford, Dalavich, Inverinan and Kilchrenan. The road serves four large blocks of forestry with a forecast timber harvest of 105,000 m3/year.
The road is due for completion at the end of September 2012 and the first wind turbines are due to arrive at the Carraig Gheal site in September 2012.
The two projects – the wind farm and the WLATHR – have a website at Link
.
The majority of funding is coming from GreenPower (Carraig Gheal) Ltd with additional co-finance from Forestry Commission Scotland and Argyll and Bute Council. Forestry Commission Scotland have awarded £1,000,000 towards the overall £5,300,000 cost from the Strategic Timber Transport Fund.
The southern limit of the WLATHR is on the A816 at Salachary and the northern limit on the B845 at Kilchrenan. When complete, the road will take about 4,200 timber lorry movements each year off the single-track roads that serve the villages of Ford, Dalavich, Inverinan and Kilchrenan. The road serves four large blocks of forestry with a forecast timber harvest of 105,000 m3/year.
The road is due for completion at the end of September 2012 and the first wind turbines are due to arrive at the Carraig Gheal site in September 2012.
The two projects – the wind farm and the WLATHR – have a website at Link
Related descriptions
- Dalriada Project
By Patrick Mackie. Used on 2 images
- Oban Airport (North Connel)
By TheTurfBurner. Used on 74 images
- May’s Wood
By Robin Stott. Used on 7 images
- Council Housing in Wolverhampton - 1930s
By John M. Used on 13 images
- Route - magna via
By Humphrey Bolton. Used on 2 images
- Loch Linnhe
By Nigel Chadwick. Used on 27 images
- National Cycle Route 78
By E Gammie. Used on 5 images
196 images use this description. Preview sample shown below:
- View these images in the Browser | On a Map
- View all images using "West Loch Awe Timber Haul Route" Shared Description(s) | (Just this description)
- Find images mentioning the words [ West Loch Awe Timber Haul Route ]
These Shared Descriptions are common to multiple images. For example, you can create a generic description for an object shown in a photo, and reuse the description on all photos of the object. All descriptions are public and shared between contributors, i.e. you can reuse a description created by others, just as they can use yours.
Created: Wed, 7 Mar 2012, Updated: Thu, 8 Mar 2012
The 'Shared Description' text on this page is Copyright 2012 Patrick Mackie, however it is specifically licensed so that contributors can reuse it on their own images without restriction.