Under the bridge
by Alan Murray-Rust
geograph for square SK5538
The tramway bridge over the railway is now in position The train is the... (more)
|
|
The bridge takes shape (4)
by Alan Murray-Rust
geograph for square SK5739
The completed concrete abutment for the new tramway bridge over the... (more)
|
|
Preparing for the bridge, Nottingham Station
by Alan Murray-Rust
geograph for square SK5739
Some of the platform buildings are being prepared for the new bridge... (more)
|
|
More progress on the bridge, March 2013 - 3
by Alan Murray-Rust
geograph for square SK5739
The short extension at the end of the truss is a temporary leader for... (more)
|
|
Lenton railway bridge site
by Alan Murray-Rust
geograph for square SK5538
The bridge deck can now be seen to be in position, but the approach... (more)
|
|
More progress on the bridge, March 2013 - 1
by Alan Murray-Rust
geograph for square SK5739
The complete span has been erected and is being finished ready for the... (more)
|
|
Lenton Junction bridge site
by Alan Murray-Rust
geograph for square SK5538
Work continues on preparing the site of the bridge to carry the new... (more)
|
|
More progress on the bridge, March 2013 - 2
by Alan Murray-Rust
geograph for square SK5739
The complete span has been erected and is being finished ready for the... (more)
|
|
More progress on the bridge, March 2013 - 5
by Alan Murray-Rust
for square SK5739
This view from Meadows Way shows the considerable length of the truss... (more)
|
|
Preparing the abutment, Station Street
by Alan Murray-Rust
geograph for square SK5739
Preparatory work for the placing of the span across Station Street. This... (more)
|
|
The bridge takes shape (6)
by Alan Murray-Rust
geograph for square SK5739
View of the new bridge works from the Tram station platform. The top of... (more)
|
|
The bridge takes shape (5)
by Alan Murray-Rust
geograph for square SK5739
One of the piers providing intermediate support for the new bridge is... (more)
|
|
Bridge foundations, Station Street
by Alan Murray-Rust
geograph for square SK5739
The first sign of genuine construction work for the new tramway... (more)
|
|
Progress at Lenton railway bridge - 3
by Alan Murray-Rust
geograph for square SK5538
A view of the complete bridge deck in the site compound on the south side... (more)
|
|
Progress at Lenton railway bridge - 2
by Alan Murray-Rust
geograph for square SK5538
The bridge deck is now on side and ready to be put in position. It... (more)
|
|
Progress at Lenton railway bridge - 1
by Alan Murray-Rust
geograph for square SK5538
The northern abutment is largely complete and work is ongoing to prepare... (more)
|
|
Preparing for the new bridge
by Alan Murray-Rust
geograph for square SK5739
Buildings have been demolished and the site cleared ready for the... (more)
|
|
Clearing the way for the bridge
by Alan Murray-Rust
for square SK5739
The site offices for the multi-storey car park construction have been... (more)
|
|
The bridge takes shape (3)
by Alan Murray-Rust
for square SK5739
A view of the bridge framework resting on its temporary supports on the... (more)
|
|
The bridge takes shape (2)
by Alan Murray-Rust
geograph for square SK5739
A closer view of the structure, with a poster with an artist's... (more)
|
|
The bridge takes shape (1)
by Alan Murray-Rust
for square SK5739
Part of the Warren truss girder bridge that will cross Nottingham Midland... (more)
|
|
Nottingham Station, tramway bridge
by Alan Murray-Rust
geograph for square SK5739
Work is still continuing on the southern pier of the main bridge. The red... (more)
|
|
Queen's Road tramway bridge
by Alan Murray-Rust
geograph for square SK5739
The red painted piers are temporary supports for the launch of the bridge... (more)
|
|
More progress on the bridge, March 2013 - 4
by Alan Murray-Rust
for square SK5739
The underside of the truss looking south from Queens Road.
|
|
Bridge construction, Station Street
by Alan Murray-Rust
geograph for square SK5739
|
|
Bridge construction, Station Street
by Alan Murray-Rust
for square SK5739
|
|
Getting ready for the launch
by Alan Murray-Rust
geograph for square SK5739
Temporary supports have been installed on the roof of platform 4/5 waiting rooms.
|