taken 8 years ago, near to Royal Leamington Spa, Warwickshire, Great Britain

Ready to reinstate part of the Parade
Ready to reinstate part of the Parade
Below the junction of Dormer Place and the Parade a major element in the sewer replacement project has been completed. Sections of new sewer have been laid and connected and the void backfilled. A wagon from Nuneaton is waiting to tip its load of hot bitmac so that the first stage of reinstating the carriageway can begin. On the left a car cautiously navigates the temporarily restricted roadspace. Up the road the orange workhorse is transferring sections of steel piling from a filled to an open part of the sewer trench. The tree in the background, centre, is a magnificent Silver Pendent Lime (Tilia petiolaris).
Leamington Spa Sewer Improvements 2010-12
Severn Trent Water is investing £7.6M in Leamington town centre to upgrade over 2.2km of the sewerage network to increase the capacity of the sewer system and reduce the risk of flooding in the town. In addition the sewer relief system will be upgraded to reduce pollution of the River Leam. Work started in September 2010 and will conclude in spring 2012.

Many of the sewers in Leamington town centre date back to Victorian times and are unable to meet the demands of today’s urban society. To meet these demands they need to be replaced with larger and more robust systems. This will reduce the risk of flooding from the town’s sewers. This is not the first time that similar works have been carried out. Since I moved to the area in 1984 there have been at least two major schemes of sewer enlargement and pollution prevention.

An essential part of the new system will be constructed in the Parade, a busy and popular shopping street in the town centre Conservation Area. Before Severn Trent can start these works, they need to divert existing gas and water mains which obstruct the proposed new sewers, and also replace old brittle mains which are nearing the end of their serviceable life. These works form Phase 1 of the scheme.

Work started on 10 January 2011. The diversion of the water mains in three locations took four weeks to complete. The diversion and replacement of the gas mains on both sides of the Parade is more complex and was expected to take around five months to complete. Works are still under way at the time of writing, July 2011.

(paraphrased from the large site notice in Euston Place Gardens, see SP3165 : Explanatory sign, Euston Place Gardens)
Creative Commons Licence [Some Rights Reserved]   © Copyright Robin Stott and licensed for reuse under this Creative Commons Licence.
1:50,000 Modern Day Landranger(TM) Map © Crown Copyright
+
+
1:50,000 Modern Day Landranger(TM) Map © Crown Copyright
TIP: Click the map for Large scale mapping
Change to interactive Map >
Grid Square
SP3165, 1614 images   (more nearby )
Photographer
  (find more nearby)
Date Taken
Tuesday, 27 September, 2011   (more nearby)
Submitted
Friday, 16 December, 2011
Geographical Context
Roads, Road transport  City, Town centre  Construction, Development  Waste, Waste management 
Place (from Tags)
Royal Leamington Spa 
Road (from Tags)
Parade 
Subject Location
OSGB36: geotagged! SP 3183 6563 [10m precision]
WGS84: 52:17.2734N 1:32.0869W
Camera Location
OSGB36: geotagged! SP 3183 6562
View Direction
North-northwest (about 337 degrees)
Looking for a postcode? Try this pageExternal link
Clickable map
+

Other Tags
Road Closure  Wagon 

Click a tag, to view other nearby images.

Image classification(about): Supplemental image
This page has been viewed about 40 times.
View this location: KML (Google Earth) · Google MapsExternal link · Bing MapsExternal link · Geograph Coverage Map · geotagged! More Links for this image
NW N NE
W Go E
SW S SE
[Mark
You are not logged in login | register