SE2636 : Ongoing sewer repair works in Morris Lane
taken 1 year ago, near to Headingley, Leeds, England

Ongoing sewer repair works in Morris Lane
These works have now been in place for 6 months.
Sewer repair on Morris Lane, Kirkstall
The Yorkshire Post reported on 12 October 2024 that a sinkhole had appeared on Morris Lane due to a collapsed sewer 7.5 metres below the road. The road, a busy through route, was closed and traffic diverted via the A65. An unofficial diversionary route via Queenswood Drive also led to considerable congestion.
Work was anticipated to last ten weeks (i.e. until Christmas 2024) but as of mid-February 2025 engineering work was still in progress and not looking like finishing any time soon.