SD8218 : Turbine Tower No 23 under construction in June 2008

taken 16 years ago, 3 km from Waterfoot, Lancashire, England

Turbine Tower No 23 under construction in June 2008
Turbine Tower No 23 under construction in June 2008
Turbine No 23 was the last of the 26 Wind Turbines to be constructed on Scout Moor.
Seen here in early June 2008 the crane prepares the site for the construction of the 26th and final tower.
Construction of Turbine No 23 had started a couple of weeks previous but due to a slight technical problem
found with the centre tower section, after the base section was installed, it was decided to leave it until last.

SD8218 : Turbine Tower No 23 construction site
SD8218 : Turbine Tower No 17 during construction in June 2008
SD8418 : The very first completed wind turbine on Scout Moor
SD7919 : Last Turbine Tower Delivery to Scout Moor
SD8219 : Turbine Tower No 26 Under Construction in May 2008

Turbine details: Tower Height: 60m
Blade Length: 40m Total Max Height: 100m
Manufacturer: Nordex
Model: N80

Scout Moor Wind Farm Construction Picture Gallery
Link

Creative Commons Licence [Some Rights Reserved]   © Copyright Paul Anderson and licensed for reuse under this Creative Commons Licence.
Category: Wind turbines
1:50,000 Modern Day Landranger(TM) Map © Crown Copyright
+
+
1:50,000 Modern Day Landranger(TM) Map © Crown Copyright
TIP: Click the map for more Large scale mapping
Grid Square
SD8218, 153 images   (more nearby 🔍)
Photographer
Paul Anderson   (more nearby)
Date Taken
Wednesday, 4 June, 2008   (more nearby)
Submitted
Thursday, 5 June, 2008
Subject Location
OSGB36: geotagged! SD 829 188 [100m precision]
WGS84: 53:39.9562N 2:15.6163W
Camera Location
OSGB36: geotagged! SD 828 188
View Direction
East-northeast (about 67 degrees)
Clickable map
+
NW N NE
W Go E
SW S SE
Image classification(about): Supplemental image
This page has been viewed about 473 times
You are not logged in login | register