SD8118 : Scout Moor Wind Farm Construction Base
taken 18 years ago, near to Edenfield, Lancashire, England
This is 1 of 2 images, with title Scout Moor Wind Farm Construction Base in this square

Scout Moor Wind Farm Construction Base
On Saturday the 31st of May 2008 the last of the twenty six turbine towers was
delivered to the Scout Moor Wind Farm construction site.
The three tower sections, seen here at the holding compound in Scout Moor quarry, were to become Turbine No 17 which was constructed during the first week of June 2008.
It was almost 6 months to the day since the first tower was delivered back in November 2007 Link
SD8218 : Completed Turbine Tower No 17 on Scout Moor
SD7919 : Last Turbine Tower Delivery to Scout Moor
SD8118 : Last Turbine Tower Section Delivery to Scout Moor
SD7919 : Turbine tower section passing Edenfield Primary School
SD8416 : Working on the Hub of Turbine No 2 at Scout Moor
SD8318 : Scout Moor Turbine Towers 15 and 21
Turbine details: Tower Height: 60m
Blade Length: 40m Total Max Height: 100m
Manufacturer: Nordex
Model: N80
Scout Moor Wind Farm Construction Picture Gallery
Link
delivered to the Scout Moor Wind Farm construction site.
The three tower sections, seen here at the holding compound in Scout Moor quarry, were to become Turbine No 17 which was constructed during the first week of June 2008.
It was almost 6 months to the day since the first tower was delivered back in November 2007 Link
SD8218 : Completed Turbine Tower No 17 on Scout Moor
SD7919 : Last Turbine Tower Delivery to Scout Moor
SD8118 : Last Turbine Tower Section Delivery to Scout Moor
SD7919 : Turbine tower section passing Edenfield Primary School
SD8416 : Working on the Hub of Turbine No 2 at Scout Moor
SD8318 : Scout Moor Turbine Towers 15 and 21
Turbine details: Tower Height: 60m
Blade Length: 40m Total Max Height: 100m
Manufacturer: Nordex
Model: N80